Dustin Clemens, Capital Projects Division Manager with the City of Asheville, has provided the following update: Despite operational challenges of maintaining traffic flow on New Haw Creek Road, progress on the sidewalk project continues steadily, and remains on track for completion in late 2026. 
For the last several months, the focus of the project has been on completing approximately 15 utility crossings, mainly for stormwater and water lines. This work requires pavement cuts and patching across New Haw Creek Road, which must be phased in order to keep the road open during lane closure restricted timeframes. To date, 8 of the approximately 15 utility crossings have been installed. 
Once utility work is complete, the contractor will be able to make faster and more visible progress. 
The recent rains did wash out some of the stone in two of the temporary patching areas, which the contractor addressed earlier this week. The City's project manager, on-site construction inspector, and the contractor will continue to monitor the construction site closely. Asphalt cuts are being patched with asphalt paving in accordance with the engineered (and NCDOT approved) plans and specifications.
The entire roadway will be repaved towards the end of the project, so the current temporary patching will not be a permanent condition.
Mr. Clemens thanks residents for their patience as the city works to improve this road for a safer pedestrian experience and a more connected community.